Morning all,
This morning I've been looking at a newly updated copy of a plan by a contractor, so as usual I use maintain baseline to import their submission last period so I can measure slippage against it. However I have noticed an issue.
plan submitted november
activity 1000 start 12-12-15 finish 31-12-15
plan submitted december
activitiy 1000 start 12-12-15A finish 4-1-16
This all makes sense however when the Nov one is imported and used as a project baseline against Dec one I get
Activity 1000 start 12-12-15A BL start 12-12-15 0 variance finish 4-1-16 BL finish 15-12-15 X amount of slippage,
as you can see the date in the baseline doesn't match the date in the november plan and when I look into it further it turns out that 15-12-15 is actually the Oct forecast date so I can't understand how or why my november plan used as a baseline is shoiwng an older date and not that in the November plan when opened seperately.
Any ideas? It's making a bit of a mockery with my trying to show slippage against last submission etc.
thanks