We keep having the issue of resource dates randomly changing. Not only do they not match the activity dates, after we fix them, a differnt batch crops up.
I realize there is the check box to "drive activity dates" for a given resource assignment. However, I don't want the resource dates to drive the activity dates, and unchecking the box isn't having the "opposite" effect of the activity dates driving the resource dates. Example.....one of my team members statused an activity with the start date of 9/27/21. However, the resource dates show an actual start of November 1. November 1 also happens to be the planned start. This is very aggravating as it's causing forecasting isssues, as well as integration issues with Cobra.
Thoughts?