Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Incorrect Duration % Complete value at WBS level

4 replies [Last post]
troon sigma
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None
Hi P6 experts, I am looking at Duration % Complete column and noticed that the activity with lowest Duration % Complete, its Duration % shows at the WBS level.  It seems that at WBS level, the software isn't calculating the correct Duration  % Complete, rather just showing Duration % of the activity that has lowest Duration % value Can someone advise on how to get correct Duration % value at the WBS level? Thanks

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

troon sigma
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None

Thanks Zoltan!

Rodel Marasigan
User offline. Last seen 1 week 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Duration % Complete = percent complete of the activity duration.

Formula = (Original Duration - Remaining Duration)/Original Duration * 100.

Note: Original Duration is taken from the current plan, not from the baseline.

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

That is correct.

However

The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far

Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP • 100) I BAC, regardless of what earned value technique is selected for the activity's WBS.

 You could create a LOE activity that spans from the 1st activity (SS) in that wbs to the last actvitiy (FF) in that wbs and look at it that way. The the duration % complete would then be correct beciase it is considering the entire tiem frame not just individual activities. The other thing to do is to create a new activity and give the ACTIVITY TYPE AS WBS SUMMARY AND IT WILL DO THE SAME THINGS AS A LOE type of activitiy.