Hi P6 experts, I am looking at Duration % Complete column and noticed that the activity with lowest Duration % Complete, its Duration % shows at the WBS level. It seems that at WBS level, the software isn't calculating the correct Duration % Complete, rather just showing Duration % of the activity that has lowest Duration % value Can someone advise on how to get correct Duration % value at the WBS level? Thanks