Activity Duration at WBS Level.

1 reply [Last post]
Anujkumar Mishra
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 16 Sep 2008
Posts: 9
I have made a Project Schedule in Primavera V-5,
Based upon the requirement of the project, I have assignd diffrenet caleders to different activities.
Same schedule has been submitted to client.
After importing this schedule in Primavera, discrepency in activity duration has been identified at WBS level of the schedule.
In my system at activity level calneders are assignde while at WBS level there is no calneder. But at clients system there is calnders at activity level as well as WBS level due to this there is difference in activity duration at WBS level of same project schedule opened at clients system and my system.

Kindly help.

Replies

Rodel Marasigan
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Anujkumar,
WBS summary band use Global Default calendar. Click below where I explained how to use Multiple calendar.
Multiple Calendar Scheduling Post#3