Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to show Baseline 2 Duration column in primavera

2 replies [Last post]
Antony Magesh
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 15 Dec 2013
Posts: 2
Groups: None

I am Comparing Initial Stage Baseline Schedule (Baseline 1) with Management Sign off baseline (Baseline 2) in Primavera.

Can anyone advise me how to show Baseline 2 Duration column in primavera.

Replies

Jerome Odeh
User offline. Last seen 7 hours 49 min ago. Offline
Joined: 19 Jan 2004
Posts: 105

Antony,

Have you tried to add a BL2 Duration UDF of data type Number or Integer and then apply a Global Change (BL2 Finish - BL2 Start) to calculate your BL2 Duration?

Downside of this workaround is that your WBS BL2 Duration will be wrong since UDF of Number/Integer types are summed.

=jerome
PlannersPlace.com

Santosh Bhat
User offline. Last seen 26 weeks 6 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

P6 can't show BL2 Durations, only BL1.

 

Project Baseline is the baseline project that all users see when they open the project. BL1 and BL2 are specific to each user and the fields that P6 calculates for BL1 and BL2 is not as extensive as for Project Baseline.