Have a project where we had some issues and had to create a "Recovery" baseline. We had set a project baseline at the beginning and had been showing the "BL Project" start and finish date columns and when I set the recovery (tertiary) baseline, went to "View", "Columns", chose BL1 start and finish colums but they just showed the original baseline dates. So I chose BL2 start and finish and they did not show the recovery baseline dates. Went so far as to restore the recovery baseline schedule, checked the dates and they were correct, so I went to "Project", "Maintain Baseline" and added it again as a baseline, went to "Project", "Assign Baselines", set it as the tertiary baseline again, tried to view the date columns and the same thing happened. Have never had this happen before and I'm stumped.
Cannot get Tertiary Baseline start & finish date columns to show up
Forum Sponsor
Top Posters
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Try showing "BL3" dates instead of BL2
Project Baseline = BL Project
Primary = BL1
Secondary = BL2
Tertiary = BL3
Cheers,
G