Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cannot get Tertiary Baseline start & finish date columns to show up

1 reply [Last post]
Robert McGhee
User offline. Last seen 8 years 49 weeks ago. Offline
Joined: 27 Mar 2008
Posts: 15
Groups: None

Have a project where we had some issues and had to create a "Recovery" baseline.  We had set a project baseline at the beginning and had been showing the "BL Project" start and finish date columns and when I set the recovery (tertiary) baseline, went to "View", "Columns", chose BL1 start and finish colums but they just showed the original baseline dates.  So I chose BL2 start and finish and they did not show the recovery baseline dates.  Went so far as to restore the recovery baseline schedule, checked the dates and they were correct, so I went to "Project", "Maintain Baseline" and added it again as a baseline, went to "Project", "Assign Baselines", set it as the tertiary baseline again, tried to view the date columns and the same thing happened.  Have never had this happen before and I'm stumped.  

Replies

Gary Whitehead
User offline. Last seen 5 years 24 weeks ago. Offline

Try showing "BL3" dates instead of BL2

Project Baseline = BL Project

Primary = BL1

Secondary = BL2

Tertiary = BL3

 

Cheers,

 

G