Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How can I show the late baseline bar on the layout?

4 replies [Last post]
Ayman Eleish
User offline. Last seen 12 years 35 weeks ago. Offline
Joined: 28 Dec 2010
Posts: 48
Groups: None

Dear All ,

Can I show the late baseline bar on the layout?

Thanks and Regards,

Replies

David Kelly
User offline. Last seen 2 years 16 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Copy the baseline you want the dates from (P6 v7 lets you do this in place)

Restore the baseline to the live EPS

Open the project you just restored

Run a global change to set :

Planned start = Late Start

Planned Finish = Late Finish

Demote the project to being a baseline again

Use that baseline - set it as secondary or tertiary - and as with ALL BASELINES it uses the planned dates to draw a bar.

Ferdinand U.
User offline. Last seen 7 years 12 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142

you can try to create UDF for late bar using excel import/export copied from your baseline late dates

Ferdinand U.
User offline. Last seen 7 years 12 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142

you can try to create UDF for late bar using excel import/export copied from your baseline late dates