I've imported a new project and I have started to update the progress. I've had a few problems:
1. When I update the actual units on an activity the actuals are added on to the at completion instead of taken away from at completion units. In other projects the at completion remains the same and the remaining units is updated automatically. I have the project setting to 'Subtract Actual from At Completion' but it doesn't seem to make any difference.
2. When I update an activity as started, with 50% complete and schedule the project, the activity is brought back to the data date rather than starting on the planned start date. Is there a setting for this? I have checked user preferences etc and can't seem to find anyway to change this
The new project does not update the same way as other projects. Not sure if it's to do with the import or the settings.
Any help would be appreciated.
Thanks
Replies