Hello everyone,
this is my first post on this forum but I've been coming here for years when I was looking for some answers. I've been using the search tool but as I couldn't find anything I thought I would ask your opinion.
Normally when I create an activity I assign a resource and a Budgeted cost. Every monthly updates I would update actual costs and the remaining costs would be calculated accordingly (Remaining = Budget - Actuals).
However if I ever modify the Remaining costs (deconnecting it from Budget costs), or on some specific activities it seems that when I update actuals the remaining costs will stay fixed as if carved in stone.
Is there a setting that affects the way Remaining costs are calculated per activity? (I know this is not a project settings as I have other activities calculating Remaining costs the "usual" way in the same project)
Thanks in advance.
Replies