Automatic Updation

5 replies [Last post]
Arun Vasanth
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Dear friends

How we can do the automatic updation for the comparison of planned progress Vs Actual progress.

With regards
Arun.V

Replies

MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Paul,

User seldom to check the display baseline bar match the original programme or not, especially if it is a large network.

Support your finding, not recommend any in-progress or completed project to be baseline
Arun Vasanth
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
thnx paul
Paul Harris
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
I strongly recommed against using Update Progress or the Apply Actuals function in P6 as these may change actual dates and unfortunately does not work exactly the same way as P3, SureTrak or MSP. This issue is all tied up with the Planned Dates which I would like to see removed from the software all toghether.

There is a technical article on my websites titled "Issues and Solutions facing Construction Contractors Implementing Primavera P6" which explains what happens, see slide 51.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.primavera.com.au - an Oracle Primavera scheduling software resources web site
Arun Vasanth
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Thnxs Alex
Thnxs Planning planet

Arun.V