Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Import xer updates the project calendars though import option is set to 'Keep existing'

1 reply [Last post]
Parthiban Sekar
User offline. Last seen 6 years 39 weeks ago. Offline

Hi,

In Primavera 15 R2,  say we have Project A with project calendar 'Cal'

Export this project to xer file.

then make some changes to 'Cal' in the Project A.

Now import the xer file and in the import option project data-Calendars 'keep existing' and update the existing project Project A in the import.

We expect that te Cal should not be updated, however it is updating..

Is this the case from the previous versions as well..?

 

Thanks

Parthi

 

 

 

 

Replies

Zoltan Palffy
User offline. Last seen 10 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that you have the proper righst to do this