Best import and export selection options - how to keep it the way the client has it without adding your codes to their project?
Best import and export selection options - how to keep it the way the client has it without adding your codes to their project?
you have 2 options
option #1
copy the project then delete the codes then export it and give it to the client
option #2
during the import process on the Update Project Options have the client select modify
in the data type: global under the Assignment Code click in the action column and change the action to do not import
also under the Assignment Code Values click in the action column and change the action to do not import
in the data type: Project under the Activity Code Values click in the action column and change the action to do not import
also under the Activity Codes click in the action column and change the action to do not import