My project has only two main wbs, building and sitework
i first created building wbs and the wbs under it
then i created site
but now it shows site on top of building wbs. both in wbs view or the activity view. how can i bring sitework to below buuilding wbs?
select Project Resource assignmenst get what you want and roll it up
go to the furst month and the first data highlight it and hold both the shift key and the control key and then scroll to the right and select the last month and the data below the last month so all of it is highlighted. Next select edit then copy
now open excel and select paste
Hi,
Why when we select resource usage spreadsheet and copy in excel, the weekly/monthy distribution have not been copied in excel?
any solution?
Hi,
Why when we select resource usage spreadsheet and copy in excel, the weekly/monthy distribution will be copied in excel?
any solution?
Hi,
What is easy way to shift/change a defined activity to WBS in P6?
Please kindly answer my question.
Project --> WBS
Select WBS you want to change
See the arrows near the end of Gantt chart portion.
Select appropiate arrow.
Click following link.
Primavera P6 moving WBS nodes up and down
or
or
Shortcut for moving WBS element
There are many ways to skin a cat.
i opened wbs tab but i do not see any arrows
P6 - Structuring Projects
Go to edit a work breakdown structure element.
Edit a work breakdown structure element
1. Choose Project, WBS.
2. Select the WBS element you want to edit. To change the element's position in the WBS, click the appropriate arrow buttons.