Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why can't I open two projects and copy activities from one to the other? pastes into the same...

No replies
John Reeves
User offline. Last seen 21 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Why can't I open two projects and copy activities from one to the other?  the 2nd is just a later update, tries to paste back into the same project... - this should be easy, like from one spreadsheet to another - is there a trick to this?  Pastes it back into the same one and want to just rename the activities....I guess I could export and import but surely there is an easier way....

John Reeves
User offline. Last seen 21 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Wow, fastest answer ever on this site.  Thank you very much.

John Reeves
User offline. Last seen 21 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Wow, fastest answer ever on this site.  Thank you very much.

david kelly
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

Yes there is a trick. Some of this might not be necessary now, but I always:

Group and sort by WBS
Do not 'hide if empty'
Always select using the left mouse button, before right-clicking and paste