In P6 can you copy resources from activity to activity?

7 replies [Last post]
Neil Deaville
User offline. Last seen 13 years 25 weeks ago. Offline
Joined: 9 Oct 2007
Posts: 17
Hi

In P6 can you copy resources from activity to activity?

I know that you can’t do this in P5, but in P6 is it possible?

A couple of our guys went on a P6 course back in January and were sure they were shown how to do it, but can’t remember now.

Thanks

Neil

Replies

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Neil
Maybe it’s not the way you intended.
View "Activities" --> On the right side of the Primavera Window you find the icon "Assign Resources". --> select the activities where you want to replace a resource (by filter or just manually) --> select the resource to be replaced --> Click onto the icon "replace" (just above the help-icon) --> select the resource to be assigned to those activities.
This window can remain open while you run different filters, sort or select different activities.
Regards
Dieter
Neil Deaville
User offline. Last seen 13 years 25 weeks ago. Offline
Joined: 9 Oct 2007
Posts: 17
I think I need to rephrase the question.

How do i move resources between activities?Thanks

Neil
Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147


Ya it’s okey. Copy & Paste is almost the same with Cut & paste.
Neil Deaville
User offline. Last seen 13 years 25 weeks ago. Offline
Joined: 9 Oct 2007
Posts: 17
Hi Arnold

I can’t seem to get this to work. I just get a copy of the activity.

Regards

Neil
Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Neil,

Yes you can.. Including Resources.

1. Open the two projects you wanted to cut & paste activity.
2. In P6 Activity Window, select the activity & right click select Cut.
3. Paste the cut activity into another project in the same activity window.

However, If you cut these activities & paste it to another project then you will loss these activities from its original project. To avoid this, make a backup copy of the original project.

HTH.

Arnold
Neil Deaville
User offline. Last seen 13 years 25 weeks ago. Offline
Joined: 9 Oct 2007
Posts: 17
Perhaps I should have said move activities; e.g. cut them from one activity and paste on another.
Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

What do you mean, copy resources from activity to activity?
You can copy the resources assigned to each activity if you will copy/paste the activities by checking all the boxes in Copy Activity option.