Zero Duration % complete

5 replies [Last post]
Paul Zacharia
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 12 Jul 2014
Posts: 19

Hii,

I get 0 duration % complete for one particular set of activity codes at the WBS level, but all other activities which are in progress/ completed rolls up to some value in the WBS level.

The activity type assiged is Fixed Durations & Units for all activities.

Please advice.

Paul

Replies

Zoltan Palffy
User offline. Last seen 9 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I am not sure what you are trying to summarize in terms of % complete but some things can not be summarized by % complete becasue you can use 3 different types of % complete. Duration % Complete, physical % complete and unit % complete by tring to do this would be like mixing apples, oranges and pears.

The summary band for either Schedule % complete or Performance % complete will always be calculated as 

(BCWS  * 100) /BAC so it would be Budgeted Cost for Work Scheduled times 100 divided by Budget at Completion

Paul Zacharia
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 12 Jul 2014
Posts: 19

I am using Duration % complete. 

Zoltan Palffy
User offline. Last seen 9 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if you are using physical % complete you can run a global change 

where

duration % Complete equal physical % complete

Paul Zacharia
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 12 Jul 2014
Posts: 19

I ran the Global change. But then the other WBSs which were showing some value for Duration % complete also increased to a non realistic value (66%), where most of the activities are not yet started / completed. 

The program is not resource and cost loaded and hence i cant get the performance % complete.

Could you please suggest any other solution. 

Thanks,

Paul.

 

 

 

Zoltan Palffy
User offline. Last seen 9 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Your Original duration and your remaing durations are equal causing the % complete to be equal.

Hence Performance % = Activity % Complete = Duration % Complete =  (OD - RD) /OD = 0%

to fix this run a global change 

where

planned start = start
planned finish = finish

this will allow the WBS summary activity to calculate a correct Percent complete value