Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

original duration become zero

1 reply [Last post]
ferhat acici
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 28 Nov 2012
Posts: 13
Groups: None

hi guys

After entering budgeted cost value to an activity, original duration shall become zero.whats the problem?

 

thnx

Replies

Zoltan Palffy
User offline. Last seen 9 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that your project is open

go to the projects directory

make sure that your project is highlighted

select view show on bottom 

click on the defaults tab

for the duration type change it to Fixed Durations & Units

go back to the activities directory

filter for ALL activities

add a column for duration tpye

on the top activity in the duration type column double click and select Fixed Durations & Units

no do a fill down for the rest of the activities

this should solve your problem