Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

planned labour cost reverts to zero after duration change - WHY?

1 reply [Last post]
Dean Pearcy
User offline. Last seen 2 years 22 weeks ago. Offline
Joined: 23 Mar 2006
Posts: 38
Groups: None

I have numerous activities that contain a labour resource, say GANG1, that don't have a resource rate as a price is meaningless in this case. It's 2 men and a van, going on maintenance activities. I then know the budget of the 3d activity of work they are doing, say £6000. so I put this figure into the planned labour cost. If i then change this activity duration to 2d, the planned cost will revert to zero. I want the planned cost to stay the same, as that is how much this task will cost. Why does it revert to zero? What auto calculation is going on that I need to stop?

Many thanks in advance.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

turn off calculate cost from units 

you wil have to change this in the resources directory add a column for Calculate costs frorm units.

 

Also under the details tab on the right where it says profile uncheck calcluate costs from units

 

Also at the activity level you want to run a global change 

where resource equals GANG1

then calculate costs from units equals no