Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to clear the "Unsatisfied Relationship" in schedule log?

2 replies [Last post]
Richard Chen
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 2 Jan 2015
Posts: 4
Groups: None

Hi all:

 

I am a planner from Taiwan, and in a Sabic project by now.

The client requested me to clear all the Unsatisfied Relationship in schedule log.

I tried many times by still can't find a logical way to clear it all.

THANKS FOR YOUR KINDLY HELP~

 

1. What is the definition of "Unsatisfied Relationship"?

2. How to clear it in schedule log?

Replies

Richard Chen
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 2 Jan 2015
Posts: 4
Groups: None

Thanks Gong,

I cleared some "unsatisfied relationship" by your way.

 

I found that A is predecessor and B is successor, A connects to B with FF relationship.

IF B has a actual start, the FF relationship will be defined as "unsatisfied relationship".

Only I can do is to remove the relationship or change the relationship to SS.

Yanqing Gong
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 20 Mar 2012
Posts: 10

Hi, Chen,

I also encountered this problem, and found that when I remove the "SS" relationship linked to the completed activity, the corresponding "Unsatisfied Relationship in schedule log" would disappear. You can have a try.Hope this can help you.