Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How do tie together the P6 Schedule, Submittal Schedule Log, & the SOV? they have redundant info - a code?

1 reply [Last post]
John Reeves
User offline. Last seen 13 weeks 10 hours ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

How do tie together the P6 Schedule, Submittal Schedule Log, & the SOV?  they have redundant info - a code?  A code could tie them together but how?  Sometimes multiple schedule items belong to only one SOV and vice versa - you could put the sched id in the sov and the sov number in the schedule but couldn't there be one similar code?  I think InEight might do something like this but I am not sure.

Replies

Rodel Marasigan
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

The SOV and CBS is defined under Cost Account and assigned into Resources of each activity. WBS is also define separately under WBS module. You can assign multiple resources into activity with different cost account and same thing with activity, you can assign Cost account into single resource assigned to multiple activity.

See below sample for your reference.

Cost-Account