Hello;
I am starting to add budgeted labor units to my schedule. The activities have a duration type of "Fixed Duration and Units/Time.
I set up my resource id's and assigned them to the activities. When I go to add the budgeted labor units of say 100 , the budgetd labor units column says 80. When I look at the detail I see the electrician has 100 budgeted labor units.
User Preferences are:
Resource Anaysis Tab
Opened Projects Only
Remaining Early dates
Custom Role Limit
Calculations Tab:
Recalcutate the units...
Assignements are both set to ask
Project Settings are: Calculations
Link Budget at completion
Reset Remaining Durations and Units to Original
Subtract Actual from At Completion
Link Actual to date and actual this period units and cost.
I cannot find that this is a setting feature - the resource calander is a standard 5 day workweek - and I have created new calendars. Is there a setting Im missing?
this is based on your resource and what you have set for Default Units/Time if it is set to 8/d
then it takes 8*the duration and give the manhours
so fo the duration is 10 days the 8*10= 80 manhours or units
you can change them manually or do them all at once then export to excel change the manhours save it then import back into P6