Hello;
I am starting to add budgeted labor units to my schedule. The activities have a duration type of "Fixed Duration and Units/Time.
I set up my resource id's and assigned them to the activities. When I go to add the budgeted labor units of say 100 , the budgetd labor units column says 80. When I look at the detail I see the electrician has 100 budgeted labor units.
User Preferences are:
Resource Anaysis Tab
Opened Projects Only
Remaining Early dates
Custom Role Limit
Calculations Tab:
Recalcutate the units...
Assignements are both set to ask
Project Settings are: Calculations
Link Budget at completion
Reset Remaining Durations and Units to Original
Subtract Actual from At Completion
Link Actual to date and actual this period units and cost.
I cannot find that this is a setting feature - the resource calander is a standard 5 day workweek - and I have created new calendars. Is there a setting Im missing?
A bit more detailed explanation please, Cynthia.
You add an actvity with what duration on what calendar
Then you add a resouirce assignmnet record, with a resource on what calendar
you add 100mhr into whiich field
Which budegeted labour units field (resource or activity) then says 80, or is it both