Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Create shift work

1 reply [Last post]
vinod raturi
User offline. Last seen 6 years 25 weeks ago. Offline
Joined: 14 Aug 2006
Posts: 57
I am unable to create work in shifts for eg I have two shifts running in our plant

First shift is from 6:00 AM to 6:00 PM and second shift from 6:00 PM to next day 6:00 AM.

can someone tell me how to enter these timing in "change working time" dialog box.

Replies

Zhang Haixiang
User offline. Last seen 3 years 49 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
Hello,
in "change working time" dialog box,select all the days,you want to change, then type in the time in "from" "to" area.(start from 0:00 ), this will change the working time for the selected days. and the day will be shaded to show that the working time was changed, see left "legend "
there’s a standard "night shift" calender in MSP,check it to see how it works.