Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Night shift

4 replies [Last post]
Stuart Atkinson
User offline. Last seen 6 weeks 4 days ago. Offline
Joined: 16 Jan 2004
Posts: 68
I need to create a night shift task calendar starting at 20;45 and ending 5:30 the next day. As it is obvious I am new to project, please take pity***

Thanks

Stuart

P.S. How will it affect re-scheduling with tasks of different calendars?

Replies

dale holmes
User offline. Last seen 13 years 49 weeks ago. Offline
Joined: 27 Sep 2007
Posts: 6
Groups: None
Thanx. that makes sense. just needed to say it outloud to see how the logic works.
Paul Harris
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
Dale

If you want to do this for 5 days the calendar settings would be;

Sunday work is 8:00pm to midnight
Monday is Midnight to 6:00am
Tuesday to Thursday as Monday
Friday is Midnight to 6:00am

Look at the MSP Night Shift Calendar this will give you a lead.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
dale holmes
User offline. Last seen 13 years 49 weeks ago. Offline
Joined: 27 Sep 2007
Posts: 6
Groups: None
can i just expand on the question. i wish to start work at 20:00 (8pm) and finish 06:00 (6am). However MS Project will not allow me to do this, telling me that my end time must be after my start time, how can it set my working day to for example.

07:00 to 12:00
12:30 to 17:00
17:30 to 20:00
20:30 to 02:00
Paul Harris
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
If you have a standard load of MSP then have a look at how MSP creates the Night shift calendar in “Project 1” when you open the software.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au