Actual Work

1 reply [Last post]
Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Is there any way of LOCKING the actual work field. Whenever I explore changes in resources, time, duration - my (past)actual work figures alter.

Replies

David Barry
User offline. Last seen 20 years 33 weeks ago. Offline
Joined: 29 Feb 2004
Posts: 3
Groups: None
Make sure "effort driven scheduling" is not operational.