descoping of work

8 replies [Last post]
kamarudhen kalapp...
User offline. Last seen 15 years 10 weeks ago. Offline
Joined: 29 Aug 2009
Posts: 3
Dear all
in one of our projects, Client awarded one particular item of work to another contractor after descoping from us in the very beginning of the Project.As this Project is lum sum contract, please advise the Contractor’s entitlement derived from this subject

Kamarudheen

Replies

ashraf alawady
User offline. Last seen 10 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Dear Raviraj Bhedase ,

in UAE,we have many cases the contractora are submitting the claims for omission of part of the original scope of works and it is not allowed to give the deleted parts to another contractor to do it .in some cases we are awaitting until the project is completed and handed pver to the client so we can give the deleted portion to another contractor.
A D
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Ashraf,

U r correct in one way, but employer / engineer can reduce scope of works and can award to other contractor. The main contractor in this case can claim for his losses but then client will certainly claim LD’s on a/c of slow progress.

But, in this part of the world, normally contractors dont claim for this loss, as the works are huge and Client dont pay on time; Contractor dont have good contracting staff and end-up loosing scope of works.
ashraf alawady
User offline. Last seen 10 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Dear all,
as per tjhe general condition of contract clause 51,the employer/the engineer has no right to omit part of the original scope of work if the omitted wok is to be carried out by the employer or by another contractor.

the contractor can reserve his right and claim for all losses related to unauthorized vairation.
Shah. HB
User offline. Last seen 1 year 19 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Alright Thanks Mr.Raviraj
A D
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
In layman language, Removal of some items from ur BOQ

Like say, u r doing a pipeline project of 200km. Client may "De-Scope" 50km and can award to some other contractor. This generally happens in this part of the world, if there is slow progress of works and contractor is not in a position to mitigate those delays

Cheers,
Shah. HB
User offline. Last seen 1 year 19 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
what does descoping mean?
Andrew Flowerdew
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Kamarudhen,

It may surprise you but the starting point is that the contractor is still entitled to the full amount of his lump sum.

Lump sum contract - risk of quantities is usually with the contractor - if so, when they go up, contractor loses as he gets no more money, when they go down, contractor gains as he’s paid all the lump sum. Contractor took the risk, contractor wins or loses.

But that’s the starting point, possibly not the end point - more likely your contract is a lump sum that can be varied and you’ll have to refer to the variation clauses to find out exactly what happens and see if this situation is covered or not.

You said "Client awarded one particular item of work to another contractor after descoping from us in the very beginning of the Project" is allowed under your contract - from your statement it reads as if the contract was already signed before this happened and this will be significant.
Samer Zawaydeh
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear kamarudhen,

The first issue is that you have to approve the change order for the removal of the scope from your contract. The financial part will follow.

Even for a lump sum contract you will need a BOQ to price your contract. Hopefully this is prepared by your client and is priced by you (Contractor) and is included in the Contract Documents.

Your Overheads are the running costs (site and office) for this project. This you must pay wether you had this item or not. You will need to clearly provide the client with the analysis and supporting documents for these costs and the weighted percentage of this cost given to the item that was deducted from your scope. Or the client can approve the standard norm of the industry in your area.

Loss of profit from completing this item is another issue that you can claim. You will need to submit an analysis with the supporting documents for the cost of this item in your BOQ (if it exist). The client can negotiate this item with you.

Let us know if you have a more specific question.

With kind regards,

Samer