Forensic Planner / Delay Analyst, Lend Lease, Cape Lambert Rail Expansion Earthworks

START Date: 
June, 2013
END Date: 
February, 2014

Forensic Planner(3 months full time & as required through Mediation process), 6/2013 to 2/2014

Defense and implementation support for “Extension of Time” claim

Selected Accomplishments:

Introduction of Bill of quantities values of various types of earthworks values from estimates into various Primavera updated schedules.

Conversion of various earthworks units of measure into “Mass Haul” values and re-introduce these values into various updated schedules.

Build various graphical outputs of “Planned vs Actual” units of measure in defense of claims.

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
350
Experience Hours (Forensic Analysis): 
1000