Associate and Claims Planner (Senior), PLANNING.COM.PL, Civil, Industrial, Infrastructure & Power Works, Rail, Road

START Date: 
October, 2002

Claim Management

  • Create Analysis of Critical & Longest path network
  • Create Time Impact Analysis (EoT)
  • Prepare/create partial contractual time claims based on delays derived from subcontractor’s Schedule.
  • Prepare general time claims based on contractual Schedule approved by the Client/Investor.
  • Prepare time claims based on baseline and updated schedule (EoT).
  • Prepare financial claims based on partial and general time claims.
  • Support in Adjudication, Conciliation, Arbitration or Litigation

 

Risk Management

  • Prepare risks analysis of time, resources and budget associated with schedule, scope, contracts, expenses, cash flow, revenues, quality control, safety and security in order to contribute towards formulation of a risk management strategy for the project.
  • Prepare alternatives and options for effective management of selected risk aspects and discuss these with the Infrastructure Project Manager for selection of the most suitable option.