Early & Late "banana curve"

2 replies [Last post]
Chris Mercer
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 2 Jun 2011
Posts: 2

Hi - I'm looking to produce banana curves (early and late date envelope) as part of the project controls suite of metrics using Powerproject. I used to produce these in P6 using activity count resource in the Resource Assignment spreadsheet window and then exported to Excel for graphing.

I've assigned an activity count to the remaining activities in the programme as a consumable resource but then am drawing a blank when it comes to getting the AC spread for the planned early and late date (ideally in a tabular fashion).

Has any one any ideas/done something similar?

Many Thanks

Replies

Rafael Davila
User offline. Last seen 3 weeks 7 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Andrew Owenson
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 18 Jun 2008
Posts: 68
Groups: None

Hi Chris

 

You could use the EA Reporter under the Project Tab. Make sure you select the duration as the quantity to report on. You will need to baseline the project first.

When you get to the baselines section report against the baseline you just did - ASAP baseline (top selection), and make sure that "use float end dates from my ASAP baseline is selcted (bottom selection). Choose current view & run.

 

The results will depend on how well your netwrok is linked.

 

Good luck

 

Regards

 

Andrew