Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Planned values of Early & Late curves Vs Actual value

1 reply [Last post]
Kannan CP
User offline. Last seen 16 weeks 4 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Interpretation of Progress S-Curve without Schedule

Case-1  the actual overall actual progress value of reporting period is less than the overall early planned value but above the overall late planned  value:  the agreed baseline completion of Project may or may not get extended, all depends on the progress achieved on the planned critical path.

Case-2  the overall actual value reported is below the overall late planned  value:  does it mean that the agreed Project completion date is extended, or it depends on the progress on the critical path

Appreciate your kind thoughts....

Kannan

Replies

Patrick Weaver
User offline. Last seen 14 hours 30 min ago. Offline
Joined: 18 Jan 2001
Posts: 383
Groups: None

The volume of work completed is a good indication of progress overall but you need to be using something like Earned Duration or Earned Schedule to see the potential effect. These techniques forecast completion based on performance to date and have been shown to be reliable indicators, see: https://mosaicprojects.com.au/PMKI-SCH-040.php#Process2  

However, this is different to the measure of progress on the critical path. You need both for a complete picture, but you also need to recognise the projected completion based on CPM is wildly optimisitic: https://mosaicprojects.com.au/PDF_Papers/P117_Why_Critical_Path_Scheduling_is_Wildly_Optimistic.pdf