Hi - I'm looking to produce banana curves (early and late date envelope) as part of the project controls suite of metrics using Powerproject. I used to produce these in P6 using activity count resource in the Resource Assignment spreadsheet window and then exported to Excel for graphing.
I've assigned an activity count to the remaining activities in the programme as a consumable resource but then am drawing a blank when it comes to getting the AC spread for the planned early and late date (ideally in a tabular fashion).
Has any one any ideas/done something similar?
Many Thanks