Asta - displaying trades from code libraries in printed border

4 replies [Last post]
Jamie O'Shea
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 11 Aug 2017
Posts: 3
Groups: None

How do I display the key for trades from code libraries in the printed border?

Replies

Ben Taunt
User offline. Last seen 1 year 31 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Scott,

Not currently, but we're working on adding that to the next release.

Thanks,

Ben @ Powerproject

Scott Griffin
User offline. Last seen 4 years 14 weeks ago. Offline
Joined: 10 Jan 2018
Posts: 4
Groups: None

Afternoon,

Does anyone know if this can be shown on all pages of the programme, other than just the last page ? 

 

Thanks,

Scott 

Jamie O'Shea
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 11 Aug 2017
Posts: 3
Groups: None

Thanks Mike, much appreciated.

Mike Testro
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Jamie

Welcome to planning planet.

Print>Print Options>Apperance>Legend>Tick Code Library

Best regards

Mike Testro