Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Issues with sorting by multiple Code Libraries

3 replies [Last post]
Hans van Leeuwen
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 15 Mar 2013
Posts: 8
Groups: None

Hello all,

I’m experimenting with schedules solely based on Code Libraries where tasks are defined by Code Libraries such as Activity Type, Objects and (Construction) Phases, instead of describing a task in the ‘description’ column. I’m investigating the benefits of sorting the same schedule in different sortings and filters based on those Code Libraries. 

See the example below. The natural ordered schedule features acitivities with multiple Code Libraries aligned.

1825
code_libraries_sort_01.jpg

As an example, the schedule can be sorted as follows.

1826
code_libraries_sort_02.jpg

The above image has been achieved by first sorting by Phase and then by Object. 

 

However, I want the objects to be sorted chronologically - the 'precast pile' should be above 'foundation block', based on the start dates of the activities of those objects. 

In this case, the 'Foundation block' is put above based on the alphabet. I know I can change the order from ascending to descending and vice versa, or change the objects into '01 Precast pile' and '02 Foundation block'. This is however not a solution for me, because my schedules will feature multiple object, where the order of those objects isn't always the same.

Is there a way of sorting the objects chronologically? By chronologically I mean the object with an activity with the earliest start date should be on top.

 

I'm eager to hear your suggestions!

Replies

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Hans

There may be a solution using the Formula column where you may be able to concatenate the sort data into a single string.

In excell the formula would look something like this:

+=left(a3,3)&b3

This would give the first three characters of cell a3 joined to the whole of b3.

You can combine left right and mid sections of multiple cells.

It works well with leading zeros.

I use this all the time when populating name columns with multiple sections so starting with:

Pipeline K00 > K01 on the first section it is easy to change the next to K01 > K02 right along to K 98 > K99 on the spreadsheet and then copy paste to the whole length - saves a hell of a lot of typing in the barchart.

Best regards

Mike Testro

BTW Lotus 123 is far superior to Excell.

Hans van Leeuwen
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 15 Mar 2013
Posts: 8
Groups: None

Hi Mike,

Thanks for your quick response. Your suggestion is a decent workaround when a project's schedule is finished. However, I'm looking for a generic solution, which can be applied on every (new) project and schedule. Also, I want the solution to keep working when I add new objects and activities, without adjusting the numbers in the blank column suggested by you. Therefore, the solution should include a sorting based on start dates of objects, i.e. the object which includes the activity with the earliest start date of all activities, should be the top of the schedule (within a certain Phase in this example).

I have tried sorting the schedule first on Phase, then on Start Date and lastly on Object. Logically, this sorting will not form groups with activities of the same object, because it will first sort on Start Date and then on Object. See the example below.

1827
code_libraries_sort_03.jpg

As mentioned before, in the example of the second image, I want the ‘Precast pile’ group to appear above the ‘Foundation block’ group. Any additional suggestions? 

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Hans

You can put random sets of numbers in a blank user column and sort on that.

One point - when you copy / paste text numbers from the Asta column to a spreadsheet the revert to numerals.

Best regards

Mike Testro