Can you create codes in the Library Explorer to remain permanent?

Y
Yasine Ali 👤 Member for 10 years 10 months

Hello everyone,

At the moment when I create a programme I create codes so that I can apply it to the bars.

However when I open a new project it seems that those codes dont come up in my "project view"

They re appear when I open up the project that I created them in the first place.

Is there a way that I can create them so that they appear on every project that I open up?

Hope I have said my question clearly

Thanks in advance guys

Y
Yasine Ali 👤 Member for 10 years 10 months

I found Mikes tip very helpful.

I think another way to do this would be to:

1. Open up two projects (one where you need the codes and the other that already has the codes)

2. Open up Library Explorer for both

3. Just copy and paste the whole folder of your own codes to the other library

Now it should all be available in the Project view

Y
Yasine Ali 👤 Member for 10 years 10 months

Thanks Mike, helpful answer as always.

Will be giving that a go.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Yasine

I set up a template programme with all my codes - resources - calendars etc that I need.

I open this whenever I start a new project and get to work straight away..

If I have to open someone elses programme I copy a single task from my template and all the stuff comes with it.

Best regards

Mike T.

Forum Sponsor

Top Posters

JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts