3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date: 
December, 2013

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
150

3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date: 
December, 2013

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
150

3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date: 
December, 2013

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
150

Planning Engineer, National Petrochemical Company, National Petrochemical Company

START Date: 
June, 2010
END Date: 
May, 2012

 

 

 

Cover Letter

 

Using Primavera Project Planner for enterprise® (P6 ).

 

Experience in software is the leading developer of computer-assisted thinking programs for businesses in the field of project planning, problem solving, and negotiating.

 

Maintenance Planning Engineer (Secondment), The Oman LNG LLC , The Oman LNG LLC

START Date: 
October, 2008

 

¨      Coordinating with the Process, Utility and Workshop departments for day to day planned works and make plan for next day + one month look-ahead activities.

¨      Coordinate with subcontractors in integrating their activites in the master plan.

¨      Planning standby work activities for next day+ one week which can be taken up in case planned works are disrupted due to operational requirements.

Maintenance Engineer, AGORTECH Pvt. Ltd, Construction

START Date: 
January, 2005
END Date: 
April, 2006

Responsible for INSTALLING and MAINTENANCE of the Compressors & Pumps

Provide Preventive Maintenance & Scheduling for preventive and Breakdown Maintenance

Centrifugal Pumps Replacement of mechanical seals, rotor, wearing rings, bearings, shaft alignments and complete overhaul