Electricity Transmission Substations and OHLs

3D / 4D Planning Engineer, National Grid UK, Electricity Transmission Substations and OHLs

START Date: 
November, 2010
END Date: 
March, 2017

·         Assured Contractor’s programme after contract awarded based on planning principles, Transmission Procedure 193, mandatory milestones, outages, links, budgeted cost and WBS mapping.

·         Ensured Contractor’s programmes are fit for NEC3 type of contract – Option A –E.

Experience Hours (Planning & Scheduling): 
14000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
4000