Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Progress Reporting

PLANNING ENGINEER, IMCO Engineering and Construction Co. WLL., Maintenance and Construction Project

START Date: 
August, 2008

A well presented and experienced PlanninG Engineer with over more than 9.8 years of extensive experience in the filed of Maintenance of Refinery Equipments and Execution and Shutdown Planning, Construction Project Oil and Gas Field, Oil and Gas Facilities Maintenance.

  • Planning and Scheduling
  • Maintenance of Refinery Equipments
  • Routine, Preventive ,Corrective and Shutdown Maintenance
  • Trunaround and Unscheduled Shutdown
  • Contstruction Project in Oil and Gas Field
  • Project Execuation
  • Material Management
Experience Hours (Planning & Scheduling): 
19650

Assistant Project Control Manager, DASH Engineering Phil inc and Mistui E&S, Petrochemical Projects

START Date: 
January, 2013

I've been  working as a project coordinator

Task includes:

- Team coordination of activities made in the reporting period and troubles encountered.

- Updating progress and mitigating delays.

Project Control Engineer

- Schedule Preparation using P6 with resource allocation

- Progress Calculation set-up in excel and Monthly update

- Monthly reporting

- EVM analysis

- Primavera Risk Analysis

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
550

Planner, MAS Australasia, Icthys LNG Project

START Date: 
November, 2017

Currently I am working as Planner (FIFO) for SCF-1 in Ichthys Project- onshore LNG project in Darwin. Which consists of construction of on shore production facility for INPEX operated LNG Gas Plant. The major works includes 2Nos. of LNG Trains, LPG and Condensate Plants, product storage tanks, administration facilities, Material Offloading Facility (MOF) and Jetty

 

Duties and Responsibilities

 

Experience Hours (Planning & Scheduling): 
1000

Manager - Planning and Control, AQUA DESIGNS INDIA PVT LTD, Chennai, Integrated Water Supply Scheme - Bihar - BUIDCO

START Date: 
February, 2016

1. Over all Project Planning and Control

2. Civil Contractor Finalisation and Schedule of completion discussion

3. Project Cost

4. Vendor/Contractor works expedition and Liasoning

5. Weightage Methodology and Physical Progress Calculation and Monitoring

6. Risk Logs

7. Critical path analysis and timely alarm to stake holders

8. Contractor Performance Monitoring'

9. Resource Planning

10. Progress Reports

11. Construction Coordination

Design & Planning Manager, Mansell Construction, All Regional Projects

START Date: 
March, 2007
END Date: 
June, 2010

Design & Planning Manager for all regional projects. Responsible for all tender and contract planning as well as design coordination on live D&B contracts

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
1000

Senior Consultant, Deloitte, Confidential

START Date: 
August, 2016
END Date: 
September, 2016

Kwok was part of team that developed a high-level operating model, and organisation design for a large utility capital delivery organisation responsible for £500m of projects annually. He specifically led the governance elements of the operating model design, and supported key aspects of process and organisation design. He co-facilitated design and review workshops working as part of a joint Deloitte and client team.

Contracts Manager, services & trade, Oman Muscat Airport Terminal and Hotel Project

START Date: 
February, 2015

Currently working as a contracts manager for the middle east region which includes Muscat, UAE, Qatar, Turkmenistan etc. I am currently on a advisory role for my company and i involve from pre tender stages of the project till the successful close out of contracts.

 

Experience summary

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
4750
Experience Hours (Forensic Analysis): 
5700

Project Planning Engineer, ORIENTALS ENTERPRISE WLL, Clubhouse, CONSTRUCTION OF 4 WORKSHOPS, FIRE STATION AT HALUL ISLAND

START Date: 
July, 2008
END Date: 
July, 2010

 

·         Review project work scope, contract milestones and project requirements incorporating all to the project baseline.

 

·         Develop the Work Breakdown Structure (WBS) using Primavera P3, and work with the project team in finalizing the WBS for progress measurement, monitoring, and project control.

 

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
4000

Regional Planner, Bovis Lend Lease, Various DIO projects

START Date: 
December, 2011
END Date: 
April, 2013

Responsible for the planning requirements of all jobs in the South West region for companies Defence Estates Framework contract with Defence Infrastructure Organisation. Successfully transformed the region into an efficient, controlled and quality focused part of the business that when I left was performing above company standards and regularly winning bids on the back of successful project completions.

Experience Hours (Planning & Scheduling): 
2300
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
600

Planning Engineer;Senior planning engineer; deputy planning manager, Leighton Asia Contractors, HOng Kong - Zuhai - Macau Bridge Passenger Clearence Building

START Date: 
January, 2017
END Date: 
January, 2018

Senior Planner on the Hong Kong-Zuhai-Macau Bridge Passenger Clearence Building (PCB).

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Forensic Analysis): 
450

Market Place

No results found... (try selecting a different content filter)

Syndicate content