September 2008 - September 2011 : as project control site area for Pulai Gading Field Station, part of Jambi Merang Development Gas Production Facility Joint Operating Body (JOB) PERTAMINA - TALISMAN
Preparation of Project Schedule for all disciplines like Civil, Mechanical, Electrical and Instrumentation Activities with performed task & milestones.
Plan and extract weekly / monthly look a head schedules updates & analysis.
Implement all the pre-activities of project based on process units regarding Which Includes Installation of Steel Structure for Main Pipe Rack, Sub Pipe Rack, Equipment Supporting Structure, and Plate Forms & Access Ways.
Posted Thu, 2006-07-27 06:11 by GOPIKRISHNA SAHUKAR
START Date:
July, 2006
Current Role
Working as Lead Engineer (Project Controls) and involved in Project Control activities of KGD6 – 80MMCMD Onshore Gas Terminal Project (Green field) at Kakinada (AP) commencing from Dredging works, Site Grading, Piling Works, Construction Jetty and Infrastructure facilities establishment till Commissioning of Onshore Terminal Project including Infrastructure Buildings
Responsibilities:
Interface with Construction manager, Project Control Manager and Discipline leads
Preparation of WBS, Construction Schedules and Pro