Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Reliance Industries Limited, India

Ravi Kiran Vedula

First Name: 
Ravi Kiran
Last Name: 
Vedula
Worked as a team member in commissioning team of Coker unit of new refinery in RIL.
Computed standard minimum times for various maintenance activities.
Developed Schedule Deviation Cause master for various units of refinery.
Improved PM compliance of refinery complex to 95%.
Improved availability and utilization of resources by developing a central pool of resources for whole refinery
Prepared Bill of materials for all equipments for better identification of spares and spare management.
Professional Since: 
Nov-2006 (18.2 yrs experience)
Oldest experience: 
Apr 2005 (19.7 yrs experience, WARNING: 1.6 years variance with Professional Since)
Years Experience: 
17

EPC Senior Planner, "Reliance Industries Limited, India", refinery

START Date: 
July, 2007
END Date: 
July, 2013

v  Preparing EPCO schedules with inputs from engineering and procurement departments/EP contractors in Primavera P6 & MS Project 2010.

v  Resource loading & levelling.

v  Analyzing the progress using S-Curve. Generating reports on daily, weekly & fortnightly basis depicting the Achievements, Critical Issues, Schedule Analysis, Progress Analysis, Front Analysis, Equipment Analysis and Manpower Analysis.

GOPIKRISHNA SAHUKAR

First Name: 
GOPIKRISHNA
Last Name: 
SAHUKAR

 Profile

Professional Since: 
Aug-1989 (35.4 yrs experience)
Oldest experience: 
Aug 1989 (35.4 yrs experience)
Years Experience: 
23

Project Planning Engineer, Petro Energy Contracting, "Reliance Industries Limited, India",Jindal Saw Ltd., OIL & GAS ,Pipeline & Refinary,Petro Chemical projects

START Date: 
May, 2005
END Date: 
September, 2011

 

v  Developing Level I, II, III Schedule in Primavera & MS Projects.

v  Working experience of over 35,000 activities on planning software.

v  Calculating Resource requirements like manpower and Plant & Machinery requirements for the project.

v  Liquidating the Project quantitatively across the duration as per schedule.

Anand Hegde

First Name: 
Anand
Last Name: 
Hegde
Professional Since: 
Jul-2003 (21.5 yrs experience)
Oldest experience: 
Jun 2009 (15.5 yrs experience, WARNING: 5.9 years variance with Professional Since)
Years Experience: 
1

Reliance Industries Limited, India Project Engineer

START Date: 
November, 2006
END Date: 
June, 2009
Worked as a project engineer in commissioning and start up team of new refinery. Took active part in document review, preparation of quality action plans for erection and commissioning of equipment, hydro test of all exchangers, mechanical checks of piping, steam blowing, spare codification, association to equipment,assessment, quality checks upon receipt.

Reliance Industries Limited, India Planning Engineer

START Date: 
June, 2009
END Date: 
June, 2010
I am working as Planning engg for past 12 months. Handled 8 shutdowns so far by planning, scheduling and controlling them using Planning software(MS Project). Planning and management of resources centrally for whole refinery.

Reliance Industries Limited, India Project Controls Manager

START Date: 
September, 2003
END Date: 
December, 2008
Cross-country Gas Pipeline Projects–
Worked on East West Gas Pipeline (EWPL) project having 1369 km (48” diameter) trunk line, 572 km Spur lines, 10 Compressor Stations, 38 Mainline Valves, 1414 crossings out of which 11 crossings by HDD/ Micro-tunneling.
Responsibilities:
o     Involved in scheduling, monitoring and reporting of Engineering, Procurement and Construction activities of Compressor Stations and Metering and Regulating Stations of East West Gas Pipeline Project.

Reliance Industries Limited, India Planner

START Date: 
June, 2009
Current Role

Lead Project Control Engineer, "Reliance Industries Limited, India", EPC of New Onshore Gas Plant upstream & Compression Facilities

START Date: 
July, 2006

Current Role

Working as Lead Engineer (Project Controls) and involved in Project Control activities of KGD6 – 80MMCMD Onshore Gas Terminal Project (Green field) at Kakinada (AP) commencing from Dredging works, Site Grading, Piling Works, Construction Jetty and Infrastructure facilities establishment till Commissioning of Onshore Terminal Project including Infrastructure Buildings 

Responsibilities:

  • Interface with Construction manager, Project Control Manager and Discipline leads
  • Preparation of WBS, Construction Schedules and Pro

Market Place

No results found... (try selecting a different content filter)

Syndicate content