Posted Thu, 2016-01-28 22:45 by Frederico Oliveira
START Date:
October, 2011
END Date:
July, 2015
Management of civil construction, electromechanical assembly and commissioning contracts, following the planning, measurement and execution of services, in total 8,400 m³ concrete, 3,300 tons of metal structures, 6,600 tons of equipment and boiler, 344,000 meters of cables and 35,000 m of pipe.
Coordination of a team with 6 people updating and producing many project documents: schedule, physical progress curves, WBS, histograms of equipment and labor, milestones and Capex (reduction of 8% of the budgeted cost and anticipation in the delivery of the project in nine months), acti
Iam Planning Engineer in Big Construction Company. I warked in many projects during my 17 years experience. I also did some cost control. iam preparing periodical rogress reports.
I also prepare claims and discuss them with the projects owners.