CVRD (Companhia Vale dos Rio Doce) (Brazillian Com

Planning and Controls Manager, CVRD (Companhia Vale dos Rio Doce) (Brazillian Com, Vale Carajas S11D Iron Ore Project

START Date: 
June, 2010
END Date: 
December, 2016

Experience on Vale S/A. – Canaã dos Carajás – Brazil

Planning and Controls Manager – From February/2015 to December/2016.

Experience Hours (Planning & Scheduling): 
4100
Experience Hours (Cost Management): 
11000

alexandre meirelles

First Name: 
alexandre
Last Name: 
meirelles
Professional Since: 
Mar-2008 (16.8 yrs experience)
Years Experience: 
0

Frederico Oliveira

First Name: 
Frederico
Last Name: 
Oliveira

Professional B.S in Electrical Engineering, Executive MBA in Project Management and Esp. in Safety Engineering.  English advanced and Spanish basic.

Professional with more than 10 years of experience in Industrial Project Planning, include site planning,  shutdowns and commissioning.

Electromechanical assembly Contract Management, following the execution, measurement and control services.

Experience in expediting and inspection of electromechanical equipment for the implementation of oil and gas plants, mining and power generation.

Professional Since: 
Aug-2006 (18.4 yrs experience)
Oldest experience: 
Oct 2011 (13.2 yrs experience, WARNING: 5.2 years variance with Professional Since)
Years Experience: 
46

Area Planning Engineer, CVRD (Companhia Vale dos Rio Doce) (Brazillian Com, First Line of Brucutu

START Date: 
October, 2011
END Date: 
July, 2015
  • Management of civil construction, electromechanical assembly and commissioning contracts, following the planning, measurement and execution of services, in total 8,400 m³ concrete, 3,300 tons of metal structures, 6,600 tons of equipment and boiler, 344,000 meters of cables and 35,000 m of pipe.
  • Coordination of a team with 6 people updating and producing many project documents: schedule, physical progress curves, WBS, histograms of equipment and labor, milestones and Capex (reduction of 8% of the budgeted cost and anticipation in the delivery of the project in nine months), acti
Experience Hours (Planning & Scheduling): 
1600

Cleberson Ferreira

First Name: 
Cleberson
Last Name: 
Ferreira

Professional with solid experience developed in national and multinational companies large size in the areas of Construction, Procurement, Natural Gas, Sanitation (water supply), Mining and Project Management.

I have a degree in Civil Engineering and an MBA in Management, Project Management and certified by the Project Management Institute. I have good knowledge of the English language.

Professional Since: 
May-2010 (14.7 yrs experience)
Years Experience: 
0

Henrique Lisboa

First Name: 
Henrique
Last Name: 
Lisboa
Professional Since: 
Jun-2006 (18.6 yrs experience)
Years Experience: 
0

Luiz Arruda

First Name: 
Luiz
Last Name: 
Arruda
Professional Since: 
Jan-2006 (18.9 yrs experience)
Oldest experience: 
May 2009 (15.6 yrs experience, WARNING: 3.3 years variance with Professional Since)
Years Experience: 
1

luke doyle

First Name: 
luke
Last Name: 
doyle
Professional Since: 
Jan-2007 (18.0 yrs experience)
Oldest experience: 
Mar 2009 (15.8 yrs experience, WARNING: 2.2 years variance with Professional Since)
Years Experience: 
1

CVRD (Companhia Vale dos Rio Doce) (Brazillian Com Planner

START Date: 
May, 2009
Current Role

CVRD (Companhia Vale dos Rio Doce) (Brazillian Com Planner

START Date: 
March, 2009
Current Role

Market Place

No results found... (try selecting a different content filter)

Syndicate content