START Date:
October, 2011
- Management of civil construction, electromechanical assembly and commissioning contracts, following the planning, measurement and execution of services, in total 8,400 m³ concrete, 3,300 tons of metal structures, 6,600 tons of equipment and boiler, 344,000 meters of cables and 35,000 m of pipe.
- Coordination of a team with 6 people updating and producing many project documents: schedule, physical progress curves, WBS, histograms of equipment and labor, milestones and Capex (reduction of 8% of the budgeted cost and anticipation in the delivery of the project in nine months), acti
Experience Hours (Planning & Scheduling):
1600
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Market Place
No results found... (try selecting a different content filter)
Website Development by Hunt Data Solutions and Vit-al Interactive. CMS:
Drupal THEME:
Acquia Marina