KENTZ

Site Planner, KENTZ, Outside Battery Limit Piping Installation Turbo Project SASOL 2 and 3

START Date: 
February, 2005
END Date: 
August, 2005

All aspects of Planning, Scheduling, Progress Reports, S-Curves.

Experience Hours (Planning & Scheduling): 
1150

structural foreman, CCC,kentz, & Al Kharafi National-Kuwait, mining /oil & gas

START Date: 
December, 2015

Sir,

don't have yet experience in planning i am still studying primavera 8.2 at abwab institute in Fahaheel Kuwait and it will end our class on the first week of this coming year January 2017, my previous experience is all in steel erection fabrication and electrical.

Merry christmas to all and thank you.

Experience Hours (Planning & Scheduling): 
0
Experience Hours (Cost Management): 
0

Regional Project Controls Manager, KENTZ, Several Projects in the Region

START Date: 
February, 2013
END Date: 
August, 2013

 

2013 – 2013

Regional Project Controls Manager, Kentz Group, Qatar

Roles and Responsibilities:

  • Responsible for the overall administration of the project controls function for the region or major projects basis
  • Direct the establish
Experience Hours (Planning & Scheduling): 
1200
Experience Hours (Cost Management): 
1200
Experience Hours (Forensic Analysis): 
300

Project Controls Manager, KENTZ, 532 Project Gas to Liquid and 545 project Air Separation Unit

START Date: 
March, 2009
END Date: 
June, 2010

Planning Manager for the Civils, Structural, Mechanical, Piping, Electrical, Instrumentation, Scada works during the Procurement, Construction and Commissioning phases including the management of scope change, change to forecast cost via trends and approved changes, impact on schedule and adjustment to contingency.

Experience Hours (Planning & Scheduling): 
2400
Experience Hours (Cost Management): 
2400
Experience Hours (Forensic Analysis): 
1400

Anthony Capone

First Name: 
Anthony
Last Name: 
Capone
Professional Since: 
Mar-2007 (17.7 yrs experience)
Oldest experience: 
Nov 2006 (18.1 yrs experience, WARNING: 0.3 years variance with Professional Since)
Years Experience: 
6

Project Planner, Kentz, Barrow Island - Gorgon Project

START Date: 
November, 2006

Sundar Singh

First Name: 
Sundar
Last Name: 
Singh
Professional Since: 
Jun-1997 (27.5 yrs experience)
Oldest experience: 
Jun 1997 (27.5 yrs experience)
Years Experience: 
43

Syed Ali

First Name: 
Syed
Last Name: 
Ali
Professional Since: 
Sep-2005 (19.2 yrs experience)
Years Experience: 
0

Andries Schutte

First Name: 
Andries
Last Name: 
Schutte

PROFESSIONAL

  • Royal Institution of Chartered Surveyors (UK)                                MRICS 1240134
  • Association of South African Quantity Surveyors                             PMAQS 825
  • South African Council for the Quantity Surveying Profession   &
Professional Since: 
Apr-1992 (32.7 yrs experience)
Oldest experience: 
Aug 2008 (16.3 yrs experience, WARNING: 16.3 years variance with Professional Since)
Years Experience: 
25
Guild Accreditation: 
Awaiting Applicant

Area Planning Engineer., KENTZ, (various projects)

START Date: 
January, 1998
END Date: 
December, 2000

Worked for Irish EPC Company Kentz in both Saudi Arabia and the UAE as a Planning Engineer. Worked on various projects from Ras Tanura Oil Refinery to Yanpet Expansion Power Project. All the work was performed in Primavera Project Planner 1.0 and progress measurement was calculated in excel.