Assistant Project Manager / Project Planner, Reliance Industries Limited, Petro Chemical projects

START Date: 
February, 2016
  • I have been given responsiblity of Project planner for planning and sechduling activities including project control system design and implementation , scope study,man-hour /duration estimation and overall EPC sechdule development. 
  • Preparation of detailed work Breakdown structure and organization chart preparation for site management,Resource estimation and delpoyment plan preparation and actual update/monitoring.
  • Progress Database design,update ,critical path analysis,schedule update and forecast completion , s curve development , update & Progress v
Experience Hours (Planning & Scheduling): 
5850
Experience Hours (Cost Management): 
750
Experience Hours (Forensic Analysis): 
750

Bid/Project Planning Engineer, ABB GISL, Petro Chemical projects, Various Power plant Projects

START Date: 
November, 2006
END Date: 
April, 2012
  • Effectively generated the detail Master time schedule (MTS) in Primavera in L3 – L4 level with resource allocation for EPC project.
  • Preparing & Maintaining the Detail Engineering & Procurement Register for EPC projects.
  • Established S-curves for each phase of project from Primavera using resource (Like Man Hour, Steel & Civil Quanties) and quantities for EPC Projects.
  • Preparing the Baseline Planning Package in cooperating all Contractual & Client Obligations.
  • Actively produced weekly & monthly progress reports, list of

Project Planning Engineer, Petro Energy Contracting, "Reliance Industries Limited, India",Jindal Saw Ltd., OIL & GAS ,Pipeline & Refinary,Petro Chemical projects

START Date: 
May, 2005
END Date: 
September, 2011

 

v  Developing Level I, II, III Schedule in Primavera & MS Projects.

v  Working experience of over 35,000 activities on planning software.

v  Calculating Resource requirements like manpower and Plant & Machinery requirements for the project.

v  Liquidating the Project quantitatively across the duration as per schedule.