September, 1999
Planning engineer for a fossil fired 615 MW plant at Indonesia. The schedule consisted of more than 10,000 activities. Planners from Duke Flour Daniel and TEC contributed to planning team. A brief of activities performed are described here under:
Part of planning team for a schedule with more than 10000 activities using primavera
S curves developed in Excel
Responsible for producing Monthly Progress Report for the entire project