Toyo Engineering Corporation

Toyo Engineering Corporation Lead Planner

START Date: 
May, 2008
END Date: 
August, 2009
     Establish the revised overall EPC schedule in P3 with client approval for base lining.
     Update and maintain the EPC master schedule. Generate 3 week and 90 days look-ahead construction schedule for weekly and monthly project contractual submission..
     Gather offshore engineering and procurement progress data for roll up into the master schedule.

Toyo Engineering Corporation Lead Planner

START Date: 
October, 2005
END Date: 
April, 2008
     Prepare the overall project master schedule in level 3 using Primavera based from the bench mark schedule provided by the client and its consultant during the early stage of the project.
     Gather and validate scheduling information from client; partner and affiliate companies.
     Develop a system and procedure for progress measuring subject for client approval. Define progress milestones and its corresponding percent weight values.

Toyo Engineering Corporation Senior Planner

START Date: 
July, 2002
END Date: 
February, 2004
Responsible for preparation of Miscellaneous Detailed Construction Schedule & Maintenance of Master Schedule & reporting for Jubail United Petrochemical Company (UNITED), United Olefins Complex Project – EOEG Unit.

Toyo Engineering Corporation Planner

START Date: 
March, 2008
Working as Planner/Scheduler assigned in Petrochemical project, FPSO, ongoing projects support and proposals.

Toyo Engineering Corporation Project Controls Engineer

START Date: 
August, 1997
END Date: 
September, 1999
Planning engineer for a fossil fired 615 MW plant at Indonesia. The schedule consisted of more than 10,000 activities. Planners from Duke Flour Daniel and TEC contributed to planning team. A brief of activities performed are described here under:

     Part of planning team for a schedule with more than 10000 activities using primavera
     S curves developed in Excel
     Responsible for producing Monthly Progress Report for the entire project

Toyo Engineering Corporation Project Controls Engineer

START Date: 
April, 1999
END Date: 
November, 2001
Projects Handled

Toyo Engineering Corporation Project Controls Engineer

START Date: 
April, 1997
END Date: 
April, 1999
Project handled

Market Place