Toyo Engineering Corporation Project Controls Engineer
START Date:
August, 1997
END Date:
September, 1999 Planning engineer for a fossil fired 615 MW plant at Indonesia. The schedule consisted of more than 10,000 activities. Planners from Duke Flour Daniel and TEC contributed to planning team. A brief of activities performed are described here under:
Part of planning team for a schedule with more than 10000 activities using primavera
S curves developed in Excel
Responsible for producing Monthly Progress Report for the entire project
Generation of Critical path report and subcontractor’s project integration.
Part of planning team for a schedule with more than 10000 activities using primavera
S curves developed in Excel
Responsible for producing Monthly Progress Report for the entire project
Generation of Critical path report and subcontractor’s project integration.