Project Control System Engineer, Toyo Engineering Corporation, Project Support

START Date: 
June, 2006
END Date: 
November, 2008

 

  • Managing personnel requirements and trainings on operation as well as supporting Site Construction on:
    • Spoolgen.
    • “In House” Construction Management Tools to Project Site
    • (ie. QCbase/ PipingTool/ WeldingControlSystem/ InstrumentControlManagementSystem etc)
    • eMarian Construction Module operation.
  • Conduct training on Piping Line Scheduling program operation (Oracle Base) for preparation and calculation of Line attributes such as test pressure, painting system, Insulation thickness, PWHT, Thermal treatment and non-destructive test class and other special requirement by the project according to the line list prepared by the process team.
  • Developing project baselines (schedule/cost) planning/controlling schedules & costs using Primavera
  • Developing a Subcontractors Performances Evaluation tool such as Subcontractor Database program using visual basic
  • Preparation of Piping BOQ, Painting and insulation materials using Support on Operational Test and Development for “In House” Programs (Oracle base) via internet, as a construction management tool comprising all disciplines including QA/QC from Engineering stage until Turn Over stage