Dear all,
I currently have a big project seted up. It has a total of 21,000 activities.
The current level of detail of the activities is activity type per building & floor.
What I want to achieve is to introduce somehow rooms per floor & put priorities on them.
Also activity steps.
For example the activity is: Building X03 - GR Floor - Installation of Doors
And I want to end up to:
Building X03 - Gr Floor - room 1/2/3... - Installation Of Frame
Building X03 - Gr Floor - room 1/2/3... - Installation Of Door
Building X03 - Gr Floor - room 1/2/3... - Installation Of Door Hardware
For crew detailed assignment & monitoring
The room priority should be through priority column
My question is: Can I achieve that somehow without making the existing activities phases and expanding them to the above mentioned & linking them?
Thanks & Regards,
Alexandros
Replies