how copy bands and activity all togather in one step

6 replies [Last post]
Shahzad Ahmad
User offline. Last seen 14 years 52 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi-

I am using P3.1

I want to make copy of bands and activites in one step

i am trying to copy band but it is not working only activities are copying.

Did any one expert in P3 who can guide me how to copy a Bands .

Thanks
shahzad

Replies

Gün Göksu
User offline. Last seen 2 years 1 week ago. Offline
Joined: 31 Mar 2005
Posts: 123
if the bands under the wbs are the same but located elsewhere then you need to change the wbs data of the peculiar actids for them to apply to the new band as you say it.

you can use the fill row command too.

further info is in the manuals.

regards.
Gün Göksu
Gün Göksu
User offline. Last seen 2 years 1 week ago. Offline
Joined: 31 Mar 2005
Posts: 123
It is possible in P3.
you can not copy/paste the bands.
but you can export & import the wbs or actcodes and do a reorganize.
Shahzad Ahmad
User offline. Last seen 14 years 52 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi-sajid.

i got it ...it is not possible in p3
Sajid Balma
User offline. Last seen 13 years 4 weeks ago. Offline
Joined: 8 Jun 2007
Posts: 151
Groups: None
Hi Shehzad
Have you been using P6 or P5. This can be done in P5 & p6 not in P3.
To create same layout in P3, you have no option but to set a layout based on either your WBS or activity code.
Shahzad Ahmad
User offline. Last seen 14 years 52 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hello Gun

Thanks for your prompt reply.

i want copyt past some Bands(title Bands) under my wbs bands which i had allready created.

how i can copy or ...

Thanks
Gün Göksu
User offline. Last seen 2 years 1 week ago. Offline
Joined: 31 Mar 2005
Posts: 123
Hi Shahzad,

1. you can use fragnets. this will copy the relationships as well.

2. you can export the relationships and reimport for the new actids.

band? do you mean the title band?
that gets created according to your organization settings.
for that check the wbs or the act code data.

hope the above will answer you question.