Filter activities by resources

38 replies [Last post]
Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Dear all,

is there a way to filter activities, which have certain resources assigned? E.g. I want only activities, which have resource A and B assigned

 

Replies

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Agree, better use multi-resources whenever possible.

The advantage of multi-resources is that by modifying them you can apply the modification to all or specific multi-resource assignments.  Companion resources can be as many as needed which can complicate verification.

Multi-resources are great, but not always you use them (for whatever reason) so filters are still handy.

Rafael,

to be sure that companion resources are not missed create and assign multi-resources.

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Vladimir,

Thanks, I copied your note into my reference file under specific filter notes box for future reference.

Bogdan,

Thanks, once again. I copied your note regarding the field for Assigned Resources into my reference file under project properties notes box for future reference.

Marcus,

Thanks for the reference.

Best Regards,

Rafael

Marcus Possi
User offline. Last seen 13 weeks 2 days ago. Offline
Joined: 27 Feb 2010
Posts: 76
Hi. I do think that you may find something helpfull in http://www.spiderproject.com/index.php/books in English. The majority of our work is written in Portuguese, but there is something about in our fourth edition. there is another one in English, about Spider Project WEB, but it is not the focus here. BR,

Rafael,

it can be done but in three steps.

First filter for activities that use resource C, then invert this filter, then filter for activities that use resource A keeping previous filter.

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Bogdan YOU MADE MY DAY, the filters work directly from Gantt.

Thank you. hats-off-salute-smiley-emoticon

Resource-Filter-on-Gantt

Resource-Filter-on-Gantt-A-or-C

Filter-contains-Resource-A-but-not-C    Frequently I am interested in looking for activities that have certain resource but is missing a required companion resource. If missing the companion resource then it shall be fixed.
 

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

Rafael,

In Spider it is possible. There is a Column (in the Other) group called Assigned Resources. This columns shows assigned resources similar to MS Project, see picture:

https://postimg.cc/gxhbB84Z

Then you can create filters to show activities containing only desired resources (no matter how many); however when expanding to assignments, all asignments will be visible since the filter is applied to the activities.

Here are some sample filters using this column:

  • Contains ( f_Resources ; 'A' ) and Contains ( f_Resources ; 'B' )
  • Contains ( f_Resources ; 'A' )
  • Contains ( f_Resources ; 'B' )
  • NOT Contains ( f_Resources ; 'A' )

PS I used A, B, C from Resource A, Resource B, Resource C. Using the Contains ( ; ) function you will have to specify the name of the resource as it appers in the resource table.

I think this is a reasonable solution.

Best regards,
Bogdan

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

I believe Spider Project Filters should be able to filter what I have done with Excel as I consider resource filters to be a matter of the utmost importance. Using Spider Interface, perhaps if using some kind of modifier to deal with indentation.

Complex-Filter

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

In Spider there is an option Activities with filtered links only - after filtering links when you apply this filter spider will show only activities which have visible links in the links table

Maybe Vladimir would consider creating a built-in filter similar to the one above but for resource assignments - you will filter resource assignments and then apply the filter Activities with filtered assignments only

And maybe another one named Filtered assignments only - which will show activities and assignments, but only the visible assignments.

What do you think?

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

RESOURCE FILTERS ARE EXECUTED ON RESOURCE ASSIGNMENTS VIEW
We might want to filter for:
1) Activities with certain resource: Say activities with Resource A
2) Activities with either one resource: Say activities with either Resource A or Resource B
3) Activities with all selected resources: Say activities that include Resource A and Resource B; I do not know hot to create such filter within Spider Project but can be done outside of Spider Project if using Excel.

Resource_Filters_01 Resource_Filters_01B Resource-Filters-02 Resource-Filters-03  Filter-Resource-A-B RESOURCE A&B FILTER YIELDS NONE

Resource-Filters-04  Resource-Filters-05 Resource_Filters_06

Click this line to download the Excel worksheet

Frequently I am interested in looking for activities that have certain resource but is missing another. If missing the companion resource then it shall be fixed.

FILTER-RESOURCE-A-BUT-NOT-C

Do you know a better way to filter for Activities that include Resource A and Resource B? and what about Activities that include Resource A but not Resource C?

Bogdan,

previously created formulas may be used for filtering repeatedly if necessary.

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

It might be that Planning Planet be a good place to provide additional guidance in the form of links to white papers and videos. Could be a win-win for Planning Planet, Spider Development Team as well for Spider Users.

http://www.planningplanet.com/advertisers/spider-project-team

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

You can also try Spider Project Help for information on Reference Books.

Spider-Project-User-Guide-01     Spider-Project-User-Guide-02

Reference Books are one type of document used by Spider Project stored as separate files, search on Spider Help for “Documents”.

Think of a Reference Book as a table you can transfer to a project file that contains many tables.
 
If one Reference Book, say a Filters/Formula Reference Book, contains user fields you must also transfer the corresponding user fields via another Reference Book for it to work as expected. Before transferring the UDFs, make sure there are no duplicated UDF codes if you need them to be different. You might edit the UDF codes within the Reference Book to avoid conflict, when transferring non existing codes will be created.

Any correction and clarification by Vladimir will be welcomed.

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Bogdan,

thanks! It helps a lot!

souch video instructions - is something I a missing in Spider!

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

First project instructions is a good way to start learning Spider.

Reference-Books-01

Reference Books are introduced under First project instructions.

Reference-Books-02

You transfer the Reference Books by opening the desired target schedule(s) as well as the Reference Book where you click menu Document then Data Transfer and make your choices.

Reference-Books-Data-Transfer

You can try with the following Reference Book.

http://www.mediafire.com/file/zqpb4vqwbjm2464/Filters_Lookahead.001.sdoc/file

Unfortunately Filters and Formulas are not introduced here.

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

Vladimir,

in your example the filter would be s_pln_ContractPrice <  s_pln_ContractCost

However you have a button in the filter creation window you can enter in the filter Fomulas that were previously created; how do you use them?

https://ibb.co/cLhZ07v

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

You cannot load from project.

Spider uses reference-books in order to transfer data from one project to another.

Here is are 2 sample movies:

1. How saved layouts work:

https://youtu.be/CnLRBLKag3Q

2. How to create and transfere layouts reference-books:

https://youtu.be/5mAhwhLCjUw

In conclusion, you have to create the layout which contans filters, WBS structure, WBS Level, Diagrams, columns, Gantt scale, etc.; save it in the project or in a file.

If you save it in a project you have to create a reference-book of the Layouts table in order to transfer it into another project.

If you save it into a file then you can loaded into any project without reference books.

Also form the main Spider windows you can set in the Options of new projects and documents a default Layout file which will be applied to any new project created.

Hope this clarifies some things.

Best regards,
Bogdan

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Be reminded that it is possible for activities to have both predecessors and successors yet still suffer from dangling – hence inadequate – schedule logic.  These cases – generally categorized as dangling finish and dangling start – are also known as “orphan relationships.”

In Spider Project:

  • Filter for Activities without Successor from Finish only will filter out dangling finish activities.
  • Filter for Activities witout Predecessor to Start only will filter out dangling start activities.


Filters-for-Dangling-Logic

You can make use of "Preceding activities to start" and "Succeeding activities from finish" fields to create the filters by your own.  Spider Project is very powerful software; it might have many fields you do not even imagine.
 

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

 

RE

<<you may also want to look into layouts because if you apply filters and then save the layout into the project then it will remember the filters>>

Ok, at looked at layouts. But I think I am missing feature Layout => Load from project (activate saved layout)

I have: 

Layout => Load from file

Layout => Save to file

 

Layout => Save in project

But not Layout => load from project ??

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Rafael,

thanks! 

Vladimir, is this a part of the standard Spider training?

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

I have no Spider Documentation other than Spider Help, I learned it by experimenting with sample files as well as through Planning Planet where Vladimir is always available in short time.  Once you learn the basics you will see there is no need to memorize the field names, no need to memorize formulas.  While spider has a script language I know no single command, I just record the script by typing as if recording an Excel Macro.

To get the fields while creating a filter:
Click Filter from Menu
Click Apply
Click New 
Click Field
Select field – there you will see the field names and codes

Select-Fields

I use Planning Planet to learn, at times by asking questions, at times by answering questions.  Today was good day, I learned a few things about Spider Filters I did not know.

Evgeny,

f_PredOpers - field (column) code.

Spider Project shows activity predecessors and successors in the Gantt Chart columns.

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Rafael,

your function f_PredOpers="" works very fine!

 

Question: where is it all documented? There is nothing I could find in  Spider help regarding f_PredOpers 

Bogdan, very simple example for filter defined by formula: show activities where expenses are larger than contract cost.

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

Rafael,

I don't think the name matters, the ideea is that you can created create filters by referencing other filters.

What I haven't been able to figure out so far is how to use formulas inside filters; I don't even know how it would be useful, but I suppose Vladimir will be able to give us a comperhensive answer.

Best Regards,
Bogdan

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Bodgan,

I wonder if there might be more complexity, maybe they are relational if written in this way instead of copy-paste the isntructions as text.

If a change is made on referenced filter it will notice?

What if circular references among filters are created?

It looks like they are relational.

Circular-Dependency-on-filters

I did not know, thank you once again.

Now I know I have the option to copy-paste instructions to keep them separate or use insert filter to keep them related.  A drawback is that you unknowingly can delete a related filter.  Always keep a reference book in case you need to restore some deleted filters.

Best Regards,

Rafael

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291
Rafael, maybe complex isn't the right word, compound is a better one. When I say complex filter I mean that Filter (C) is made from Filter (A) AND/OR/NOT Filter (B).
Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Bodgan,

What is the difference between what you call simple and complex filters? 

  • Perhaps you mean when using AND/OR/NOT conditions?
  • Perhaps when inserting other filters?
  • If not enough inserting functions, field[modifier] or formulas can also complicate the filter.

Best Regards,

Rafael

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

Evgeny,

you may also want to look into layouts because if you apply filters and then save the layout into the project then it will remember the filters.

For example you may want to create a 2 weeks lookahead + filter all activities that use resource B. You can either create a simple filter for these 2 conditions or 2 filters and 1 complex filter with the 2 conditions.

After this you can save the layout as 2 weeks lookahead and when you call it it will automatically apply the filters. Layouts can also store columns (order, size), level of detail of the WBS, report diagrams, scale of the gantt chart, pretty much anything.

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Evgeny,

For activitiew without predecessors the filter is.

NOPRED-FILTER-01

to mean field is empty use two quotation marks (") + (") with nothing in between, that is ""

NOPRED-FILTER-02
 

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

This is not a filter, it is more of a report, but it has some advantages in the sense that it also displays amount of resource hours, volumes of work, costs and so on and so forth.

What I am talking about is Project Truncation, you can find it the Reports and Diagrams->Project truncation.

It creates a truncation of the project between 2 dates or from data date +/- number of days.

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Evgeny,

For how to use this magic please follow the steps.

1 Filters-01 2 Filters_02

3 Filter-03-Create-Filter 4 Filter-04-Before-applying-filter Before Filter

5 Filter-05-after-filter-for-duration-greatern-than-3-days  After Filter Apply-filter

After creating a few simple filters try something more complex and come back with your questions.  Perhaps lookahead filters.

6 Filters-06 7 Filters-07

You can download the following file to explore a few look-ahead and look-back filters.

http://www.mediafire.com/file/sidwwv9lorbs0cc/Filters-A.002.sprj/file

As they do not depend on UDF you can copy and paste them into other files without any UDF code conflicts.  Or you can transfer the following Reference Book.

http://www.mediafire.com/file/zqpb4vqwbjm2464/Filters_Lookahead.001.sdoc/file

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Bogdan,

thanks! I just now need to understand how to use all this magic

Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

Evgeny,

Q1) Can I build manually filter with equivalent functionality to the one of built in filter (e.g. activities without preicessors only)?

Yes.

Q2) When I build a new filter manually, can I re-use (refer to) built in filter? E.g.: activities without preicessors only AND something else

No you cannot refer tu built in filter, but you can build any number of simple filters and then combine them into one complex filter. This complex filter can contain simple filters and formulas also.

Q3) When filter is applyed, can I see exactly which filter is applyed and which logic?

In the lower part of the window you may see which filter is applied, number of rows selected, filter on links.

If you see which filters are applyed then you know the logic.

Also you can undo filters from the Action->Undo table and you can undo them in random order. (An action once undone, it cannot be redone)

Hope this aswers your questions.

Best regards,
Bogdan

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Vladimir, Bogdan,

 

thanks! It works!

 

Just to check my understanding

1) There are built in filters, which one can access through Filter menu (e.g. activities without preicessors only etc)

2) it is also possible to build own filters by clicking filter icon

 

Questions:

Q1) Can I build manually filter with equivalent functionality to the one of built in filter (e.g. activities without preicessors only)?

Q2) When I build a new filter manually, can I re-use (refer to) built in filter? E.g.: activities without preicessors only AND something else

Q3) When filter is applyed, can I see exactly which filter is applyed and which logic?

This is another way:

Filter
Bogdan Leonte
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 18 Aug 2012
Posts: 291

Hello,

here is the full answer.

https://ibb.co/3czryJC

Also you can select any column and filter any resources that meets certain criteria.

This is easy.

In the activity Gantt Chart menu select Filter/Only activities that use ... /Resources and then choose resources in the list.